CARACAS METRO
LINE 2
(Agust 1985 to november 1987)
|
Metro
|
|
|
Participants:
|
Engineers:
Main contractor:
|
SICARTSA (Venezuela)
OCIMECA (BORIE-SAE, SGE, SPIE)
|
|
Techniques:
|
Grouting-Diaphragm wall-Anchor |
Period:
|
August 1985 to October 1987 |
|
Quantity of works:
- Drilling (for grouting
only): 400 000 ml (max. depth: 50 m)
- Cement-bentonite grouted:
14 000 m3
- Hard gel grouted: 22
600 m3
- Diaphragm wall (0,80
m thickness): 52 000 m² (max. depth: 30 m)
- Drilling (for anchors
only): 105 000 ml (max. depth: 45 m)
|
|
SPECIAL WORKS REGARDING
THE METRO LINE CONSTRUCTION..
The followings techniques
have been used:
- Diaphragm wall, anchors,
and shotcrete: execution of 4 stations and 5 ventilations.
- .Grouting for the consolidation
of 1600 m section of soils, before excavation of the tunnel.
This site is an important
evolution in the management of the grouting technic. This
page is dedicated to the grouting works only.
Géology:
- On a 1300 m section length:
sand, alterated shale and shale.
- On a 300 m section lenght:
mass of fallen rocks (Boulders & sand).
This grouting work site
is one of the first to use electronic devices and computers
to manage the design, the follow up and the analysis.
- .The whole grouting design
was made by the "CASTAUR" program (Soletanche),drawing
automatically the drillholes, taking in account the following
parameters:
- the specificatiions
- the caracteristics
of the drilling rigs
- the locations
- the geology
- the existing services
- Daily
follow up of the quantities allowing:
- Establishment of a
daily report of the quantities for the client , few
hours only after the end of the shift.
- Daily stastistics of
the progress
- Daily controls of used
products and follow up of the stocks.
- .A quick interpretation
of the geology from the results of the drilling parameters
records, allowing the adaptation of the grouting treatment.
- Improvement of the production
by the rapidity the electronic and computer.
- The possibility to manage
the grouting with local Engineers, without any knowledge
of this technique,.
- The organisation of a centralized
management allowing a homogeneity of the grouting principles
(grouting organisation).
Grouting.
Principles
- All works from the surface
(Tunnel depth: between 20 and 45 m).
- Grouting using sleeved
pipes (Tubes à machettes) of 0,33 m.
- Drillholes by group, in
fan-shaped, in a vertical plan, with a maximum space between
drillhole of 1,20 m
- Space between group: 1,20
m.
- Définition of the treatment:
- future tunnel volume
+ a peripherical cylinder of 3,00m
- Sands and alterated
shales only.
- Cement bentonite grout.
- Variable proportion of
Hard gel (relative to the soils).
Chronology of the works:
- Soil investigation by drilling
parameters recording .
- One drillhole each
5,00 m.
- Investigation by 1,50 m
depth trench, to locate existing services (water, sewage
and gaz pipes, electrical and telephone cables)
- At each group of drillholes
(every 1,20 m).
- .Definition of the treatment
by "the grouting organisation", taking in account
the soil and trench investigations:
- Arrangement and depth
of the grouting drillholes.
- Length of smooth and
sleeved pipes (TAM), for each hole).
- Grouting instructions
for each sleeve (section of 0,33m) with the following:
- Maximum pressure
- Maximum grouting
flow rate.
- maximum quantity.
- mix grout type.
- Drilling and pipe equipment
for each hole.
- After 7 days grouting of
the cement bentonite phase.
- 7 days after this phase
grouting of the hard gel phase.
- Daily analysis by the "grouting
organisation", of the grouting parameters of each sleeve.
This analysis can have the following consequencies:
- The grouting can be
considered satisfactory
- Full revision of the
grouting instructions
- Decide a new grouting
phase on the consiterated sleeve..
- Drill new hole.
On
the whole 95% of the works suceed. However the following facts
have to be noted:
- Important deviations for
drillholes longer than 45 m depth. This fact occured in
the last 30 meters of the tunnel. It was necessary to proceed
a new grouting with new instructions with changes:
- space between holes
- maximum grouting pressure
- Effect of the soil on the
grouted mixes:
- .Some components of
the hard gel mix are affected by a type of soil bacterias
and the the hard gel is not setting
|
|
| Grouting
equipment |
13
drilling rigs:
- 11 DCH 100 - 104 - 114
(Domine)
- 2 F320 (Soletanche)
72 grouting pumps: mainly
PH 2x5 (Domine)
Mélangeurs à coulis de ciment
Mélangeurs / doseurs pour gel dur
Drilling parameters recorders:
|
Personal
(grouting) |
50 expatried (variable)
500 Venezueliens
|
Thanks
Mr VENOT, JOUBAY and Gino CIUK.
Gracias
Senorita Marianella COLMENARES and Senores Pablo COLMENZANA,
Luis CASTILLO, Ruben PARILLI , Nelson AZCEVEDO Simon ??? and FERNADEZ.