TILDEN DAM

June to november 1976

DAM

new

USA
Marquette (Michigan)
Technique:
Slurry wall (cement bentonite)
Period:
July to october 1976

OBJECT

Water storage dam for mining plant.
Several small dams on 10 km lenght.

HISTORICAL.

The mining Company had to set a dam on a very permeable soil, at this period it had the following solutions:

  • Excavated and substitued the permeable soil by clay
    • this solution was not applicable under the water table level.
  • Performed a gouted curtain.
  • Performed a slury trench with bentonite mud.
    • But this is no convenient for the enbankment of the dam (no strenght)
  • Performed a slutty trench with self hardening mix.

The last solution was choosen.

Method.

Backhoe excavation to 12 m depth (thickness of the trench 0.90 m). Then making deeper with the Kelly system (Soletanche) to the bed rock (thickness of the trench 0.60 m). All excavation were made using a cement bentonite mix.

Charateristics of this work.

Difficulties:

  • To find the right cement bentonite mix
    • The standard mixes used in Europe are not applicable with american cements.
  • To adjust the mixing production with the excavating production.

Difficulté pour mettre au point le coulis. Le dosage réduit en ciment n'etant pas appliquable avec les ciments portland. ( Il a fallu doser à 250 kg /m3).

Difficulté à tenir le rendement des engins d'excavation au niveau de la production de coulis.


Solutions found.

  • Cement bentonite mix:
    • Increasing the cement proportion to 250 kg/m3.
  • Important modifications of the mixing plant.
    • Fabrication of the bentonite mud with 2 mixers of 4 m3 of capacity. Production 72 m3/h (working 7 days/ week).
    • Continuous fabrication of cement bentonite mix with 1 m3 mixer only (mud bentonite and cement screw). Producion 90 m3/h (working 5.5 days/week).
  • Adjustment of the pumping system to send the mix to 3 km.
Quantity of works:

53 750 m² excavated

Thickness: 0,90 m & 0,60 m

Maximum depth : 24 m

materiel

2 track cranes with the kelly system (Soletanche)
1 backhoe .
2 bentonite mixers (4 m3)
2 Cement bentonite mixers (1 m3)
300 tonnes ciment storage
Several pumps and tanks.

Personnel

8 French


# 50 Americans

Things:

Easy way to make conversion from International system and Anglo Saxon system, for example:

Pipe volume: Diameter of the pipe (in inches) X Diameter of the pipe (in inches) / 2 # Volume in litres of 1 m lentgh of this pipe.
Surface: 10 square feet # 1 m²